Burke-Gilman Project to Cost $2.2 Million More Than Expected

The trail is not expected to be fully reopened until the end of January; the project originally was expected to cost $2.69 million but problems found during work are causing overruns.

 

The King County Parks Department will be asking the King County Council for $2.2 million more to complete the

The project, which aims to improve a 30-year-old stretch of the Burke-Gilman Trail in Lake Forest Park, originally expected to cost $2.69 million, encountered several problems in the course of the work which began last June. If the Council approves the new costs the total price tag of the project will be about $4.89 million.

Find out what's happening in Woodinvillewith free, real-time updates from Patch.

Contractor crews have worked extended hours since September to address the problems which are in three areas. Difficulties with working around underground utilities required redesign of the stormwater systems, said project manager Gina Auld, of King County Parks. Poor soil conditions required different kinds of retaining walls to be put up. Trees along the footprint of the trail impeded the improvements and about 100 more trees than the 219 originally identified had to be removed.

King County Parks had hoped to finish the project by Dec. 31 and reopen the trail but only the stretch from Logboom Park in Kenmore to Ballinger Way is expected to be completed by then. The entire Burke-Gilman stretch in Lake Forest Park will be closed until the end of January. The paving of the trail has been completed.

Find out what's happening in Woodinvillewith free, real-time updates from Patch.

"All of those issues were significant," Auld said. "To the project schedule it added a lot of time."

The three retaining walls that require the additional cost, about $794,000, are "pilewalls," Auld said, instead of "gabion" walls which are wire baskets filled with rocks. The pilewalls consist of wood leggings inbetween vertical steel H beams.

The stormwater system improvements because of the problems working around the underground utilities will cost $430,000 more. The additional tree removal and landscaping will cost $400,000 more.

The funding sources for the cost overruns will be about $1.3 million from the what's leftover from the Eastlake Sammamish Trail project. The remaining $900,000 will be from open space bond funds, the parks capital fund, and county general fund, according to the proposal sent to the County Council, said Doug Williams, spokesman for King County Parks. 

Over the next six weeks, construction crews will be working on trail intersections with streets, curbs, gutters, sidewalks and safety features—such as concrete warning bands, signage and bollards--wood poles that prevent cars from coming onto the trail, Auld said.

More than 300 trees total have been removed, nearly 100 more than originally anticipated, but Auld said the clearing was approved by King County's arborist and Lake Forest Park's arborist. 

The trail detour from Ballinger Way Northeast to Northeast 94th St. is in effect until the project is completed. 

For more information call the project hotline at 206-462-6348 or go to the Web site, http://www.kingcounty.gov/operations/capitalImprovements/parkscip/projects/burkegilmantrail.aspx

To contact King County Councilman Bob Ferguson, who represents Lake Forest Park and will vote on the approval of additional trail funds, e-mail him at bob.ferguson@kingcounty.gov